Your inspector needs to see the roof sheathing, how it is installed, and how it is fastened. Follow these steps before anything is covered.
Start with wide views of the roof, then get close enough for your inspector to clearly see the panel layout, fasteners and spacing.
Do not assume the entire roof uses the same fastening pattern. Follow the approved structural plans and make sure the inspector can identify the different roof areas and conditions.
Whenever fastener spacing is important, include clear photos with a measuring tape placed next to the fasteners. Make sure both the tape and fasteners are visible so the inspector can verify the spacing.
Take a slow video showing all roof areas where sheathing has been installed.
Make sure we can see:
Show how the roof sheathing panels are laid out across the roof.
Make sure we can see:
Get close enough for the inspector to clearly see the nails or other approved fasteners.
Show several locations so the inspector can see that the fastening pattern continues across the roof.
Place a measuring tape next to the fasteners and take clear photos so we can verify the spacing.
Make sure we can see:
These areas can have different fastening or installation details, so make sure they are clearly visible.
Show:
If fastener spacing needs to be verified in these areas, include close-up photos with a measuring tape visible.
Show the sheathing around all openings and penetrations before they are covered.
Make sure we can see:
Show any area that has a different structural or fastening detail from the typical roof sheathing.
This may include:
If spacing is part of the special detail, include photos with a measuring tape so your inspector can verify it.
If one area of the roof looks different from the rest, make sure the inspector can see it clearly.
Take 30 seconds and make sure your inspector can clearly identify the roof areas and verify the fastening patterns.
Submit your photos, videos and measurement photos through Permit Rockstar. Your inspector will compare the roof sheathing installation and fastening patterns with the approved structural and architectural plans.