Show the completed mechanical systems that are part of your project and demonstrate that the applicable equipment, controls, air distribution and exhaust systems are operating.
Not every project has the same mechanical equipment or systems. Follow only the sections that apply to the permitted mechanical scope on your project.
If your project does not include an air-conditioning system, ductwork, exhaust fan, dryer exhaust, range hood, fresh-air system or another item listed below, simply skip that section.
Where applicable, demonstrate that the system responds to its controls and that air is moving through representative supply and return locations.
Start with a slow walkthrough of the areas included in the mechanical final.
Show whichever applies:
Show the completed equipment installation and enough surrounding area for the inspector to understand the location and access.
This may include:
Show the thermostat powered on and demonstrate that the mechanical system responds to the control.
For the video:
Give the system enough time to respond before ending the video.
Show supply registers in representative areas and demonstrate that air is moving while the system is operating.
Show:
You do not need to record every register unless the inspector specifically requests additional evidence.
Show the return-air grilles and the areas they serve.
Make sure we can see:
Show the visible condensate drainage and protection associated with the installed equipment.
Show whichever applies:
Show enough of the drain route and termination for the inspector to understand where the condensate goes.
Operate the exhaust or ventilation systems included in your project.
This may include:
Show the device or grille first, then demonstrate operation where practical.
Show the finished mechanical components that need to remain accessible for operation or service.
This may include:
If a mechanical condition is different from the typical installation, make sure your inspector can see it clearly.
Only check the items that apply to your permitted mechanical scope.
Submit the photos and videos for the mechanical systems that apply to your project through Permit Rockstar. Your inspector will review the completed installation and applicable operational testing against the approved project requirements.